In response to the increasing adoption of cost plus remuneration contract model in petrochemical projects, this paper introduces the cost plus remuneration pricing methodology and, based on experience from multiple petrochemical projects, analyzes key challenges faced by contractors, such as increased process control difficulties, cost ambiguity and complex settlement procedures, so as to achieve the goal of win-win for both parties.
Key words: engineering, cost plus remuneration, petrochemical project, cost control
Dai Fei.
Analysis of Several Expense Issues Concerning Cost Plus Remuneration Model in Petrochemical Projects #br#[J].Petrochemical Design, 2025, 42(4): 52-55.
0 / / Recommend
Add to citation manager EndNote|Reference Manager|ProCite|BibTeX|RefWorks
URL: http://syhgsj.sei.com.cn/EN/
http://syhgsj.sei.com.cn/EN/Y2025/V42/I4/52
Strategic Analysis of High Quality International Operation of Chinese Refiningand Petrochemical Engineering Companies
Cited